I am reviewing a report that has some average daily traffic volumes.
I am interested in an estimation on peak hourly volumes.
Can anyone provide a rule of thumb that give the ratio or range in ratios between these two traffic counts. The road will be in a third world country and be a toll road to US interstate standards.
My concern is that the projected increases will at some time exceed the peak capacity of the proposed roadway.
The current ADT is around 15,000 vehicles per day. This would be 7,500 each way and the proposed road would have two lanes each direction. The peak hourly capacity is about 1,600 per lane (if I remember my traffic courses from 30 years ago) and they are predicting annal increases of around 3% per year.
My problem is to determine when they will need to expand the highway to accomidate the traffic increase.
Rick Kitson MBA P.Eng
Construction Project Management
From conception to completion
I am interested in an estimation on peak hourly volumes.
Can anyone provide a rule of thumb that give the ratio or range in ratios between these two traffic counts. The road will be in a third world country and be a toll road to US interstate standards.
My concern is that the projected increases will at some time exceed the peak capacity of the proposed roadway.
The current ADT is around 15,000 vehicles per day. This would be 7,500 each way and the proposed road would have two lanes each direction. The peak hourly capacity is about 1,600 per lane (if I remember my traffic courses from 30 years ago) and they are predicting annal increases of around 3% per year.
My problem is to determine when they will need to expand the highway to accomidate the traffic increase.
Rick Kitson MBA P.Eng