what is a good period of time to wait between pouring the building footing and the building foundation/piers? Assuming no special admixtures for early high strength and we shall say normal (type 10) concrete.
thanks
DRW
what is a good period of time to wait between pouring the building footing and the building foundation/piers? Assuming no special admixtures for early high strength and we shall say normal (type 10) concrete.