stumped! how to get the whole predecessor "chain"

Status
Not open for further replies.

kevsnc

Industrial
Jul 19, 2001
1
I have some very lengthy projects involving equipment and people moves. With the people moves I have to perform staging and often have to rework based on a circular relationship with up to 25 events in the predecessor chain. MS Project will tell you that you have a circular relationship, but you must manually find each task and write it down to find all those that are part of the chain.

Is there a way to view the whole sequence of a particular chain?
 