I am working in Project Controls Area and am trying to simulate project dates taken from Primavera P3. I can make the relations for finish to start but dont know if it is possible to relate activities in other three manners i.e start to start, start to finish, finish to finish. What I am talking about is kind of mathematical model in Excel spreadsheet. I need to know if there are any formulae that can relate the activities in all four possible manners.
Raja Ahmed B.E. M.Eng.
Alberta, Canada.
I am working in Project Controls Area and am trying to simulate project dates taken from Primavera P3. I can make the relations for finish to start but dont know if it is possible to relate activities in other three manners i.e start to start, start to finish, finish to finish. What I am talking about is kind of mathematical model in Excel spreadsheet. I need to know if there are any formulae that can relate the activities in all four possible manners.