schwarz
Electrical
- Jan 14, 2002
- 29
Hi All,
We often have to size Diesel genset for telecom sites. My questions are A) how much continuous(8-12 hours) KW load (0.9PF) & no A/C can be put on a 1 PHASE 10KVA DG set. B)If we have SMPS load of 7.5KW (0.9PF) and A/C load 2KW (0.6pf) what should be min. DG set capacity in KVA &KW? Regards
We often have to size Diesel genset for telecom sites. My questions are A) how much continuous(8-12 hours) KW load (0.9PF) & no A/C can be put on a 1 PHASE 10KVA DG set. B)If we have SMPS load of 7.5KW (0.9PF) and A/C load 2KW (0.6pf) what should be min. DG set capacity in KVA &KW? Regards