I am working on a project which is an old manufacturing facility that is being dismantled, with everything being brought down to grade. The facility contains many u-drains and pits, which will remain in place, and will be backfilled. The contractor is planning to put holes in the bottom of the pits so that they don't fill with water when it rains.
They are looking for me to tell them how big to make the holes, and how far apart, and I have no idea.
Any suggestions?
Thanks in advance!
They are looking for me to tell them how big to make the holes, and how far apart, and I have no idea.