RT-4 & Compress Calcs.

Status
Not open for further replies.

PVdesigner

Mechanical
Jan 14, 2008
37
Hi All

I've got the (100' Tan-Tan) vessel whose radiography is required to be RT-4. All the category A & B welds require spot X-ray except the bottom 30' that require full X-Ray. Setting summary of compress shows me RT-3 which i couldnot understand why. Any ideas???? Thanks
 
Replies continue below

Recommended for you

ok as I remember the RT-4 stamping....it is anything that is not rt-1 rt-2 or rt-4 and it needs to be clarified,

Did you put rt-3 in a settings or did you you fill in the required for fthe bottom 30 feet sections
 
sorry....i wrote in ""it is anything that is not rt-1 rt-2 or rt-4""

it should say ""it is anything that is not rt-1 rt-2 or RT-3""
 
Thanks Vesselfab

I have assigned 100% X-ray(both A & B category welds) for the bottom 30' and 80% X-ray for rest of the welds. And as to our understanding, compress should show RT-4 instead of RT-3 in setting summary.
 