dears,
we are designing the pile foundation, where there are requirement for pile testing for
routine pile test and initial test pile.
initial test pile to be done for 2.5 times the safe load
and
routine pile test to be done for 1.5 times the safe load
i have a doubt whether the reinforcement for these test pile needs to be done 2.5 times safe load
or only for the safe load capacity?
thanks
senthilkumar