Has anyone seen the problem of trying to relevel if future task is completed? MS Project will not remove completed tasks from the resource's future workplan.
For example:
Assume all of the following tasks are performed by the same resource.
Task 1: July 1 - July 8
Task 2: July 9 - July 16
Task 3: July 17 - July 24
Task 4: July 25 - July 31
If task 3 gets completed, I do not see Task 4 get moved up a week when I re-level. MS Project will not move Task 4 into that week. Am I missing an option on a submenu somewhere?
For example:
Assume all of the following tasks are performed by the same resource.
Task 1: July 1 - July 8
Task 2: July 9 - July 16
Task 3: July 17 - July 24
Task 4: July 25 - July 31
If task 3 gets completed, I do not see Task 4 get moved up a week when I re-level. MS Project will not move Task 4 into that week. Am I missing an option on a submenu somewhere?