Resource Calendar

Status
Not open for further replies.

obede

Computer
Feb 6, 2006
4
I'm Newbie on MS Project.

The Default calendar is 8h/day but there are resources that need work 10h/day.
I changed the resource calendar but I don't get any change on project. How can I aplly the changed resource calendar?

Thank you very much

Obede