FL21USF
Civil/Environmental
- Feb 27, 2003
- 4
The work is in SW Florida. Several failing 22" & 18" clay and concrete sanitary sewer pipes were rehabbed with HDPE. However, the annular space was not grouted. In several spots the pipes have collapsed or the joints have come apart. The infiltration of sand is causing potholes in the roadways.
The client would like to CIPP the pipes. If you have any experience on removing poly-liners from collapsed pipe or have been able to rehab a similar system, I would appreciate your comments.
Thanks - Mike
The client would like to CIPP the pipes. If you have any experience on removing poly-liners from collapsed pipe or have been able to rehab a similar system, I would appreciate your comments.
Thanks - Mike