I want to standarize and improve the run test procedure and others start-up procedures for Natural Gas Reciprocating Compressors after overhaul.
1. I would like to know how many tests are needed without load and with load.( I.e 1 minute, 5 minutes, 10 minutes etc. Starts and stops for main bearing caps and connecting rod bearing caps temperature measurements)
2. How long time is needed for hot alignment procedure