gks
Chemical
- Apr 13, 2002
- 4
hey all,
As per literature (Oil Field Processing ; Vol.II : Crude Oil by F.S. Manning et all page –368 ) the recommended purge gas velocity for flare stack with molecular seal is 0.01 ft/sec t0 0.03 ft/sec. Can the same velocity criteria can be used for Unit flare header end purge of individual units in a large gas processing complex? We could not find it in API RP-521 . Will any one help us in finding the recommended purge gas velocities for Flare SUB Headers?
As per literature (Oil Field Processing ; Vol.II : Crude Oil by F.S. Manning et all page –368 ) the recommended purge gas velocity for flare stack with molecular seal is 0.01 ft/sec t0 0.03 ft/sec. Can the same velocity criteria can be used for Unit flare header end purge of individual units in a large gas processing complex? We could not find it in API RP-521 . Will any one help us in finding the recommended purge gas velocities for Flare SUB Headers?