Hi. At first, sorry, my english isn´t very gook, I know.
OK, I´m working with "Microsoft project 2002". I need to know START and FINISH date for every task referred to START PROJECT DATE.
When the project begins, it´s "DAY 1", the next day is "DAY 2"...
For example, a task begins at DAY 45, and finishes at "DAY 48".
Anybody knows how I could know that automatically, for all tasks?
Thanks a lot.