I have a class B 40' 2.25 treated piling driven 22' into the ground and cemented. The top of the piling is 12" diameter and the driven bottom is 7". The piling is 5 3/4" out of alignment and I would like to pull it into line using a come along and chain. The chain will be fixed to the top of the piling and the come along to the bottom of the sister piling that is 15' away.
How much pull can the piling take before cracking?
Is it feasible to try to pull it 5 3/4" without causing permanent damage?
Is there a formula that can be used to hypothetically design a pull criteria?
Thanks,
Tony