PDMworks Workgroup Question 1

Status
Not open for further replies.

draftsman2008

Mechanical
Jan 29, 2008
45
We are getting ready to implement PDMworks Workgroup at work. We us Jobboss to create travelers for the shop and Jobboss uses AutoVue to view and print attachments, we attach the drawings to the traveler in the system so that when someone prints a traveler the drawings also print.

Our problem with this is that Jobboss and AutoVue will not be able to access the vault to print the drawings.

I know that PDMworks will create a pdf in the vault upon checking in a drawing.

My questions is there a way to get it to create a pdf outside of the vault?

If not, is there a way to use Solidworks Scheduler to print to a pdf outside of the vault so that we cad attach the pdf to our travelers?

If so, is there a way to tell it to only print files that have been modified on a curtain day?

Brian
Dell Optiplex 745
Intel Core 2 6300 @ 1.86 GHz 2 gig Ram
Solidworks 2007 SP 5 & 2008 SP 3.1
AutoCAD Mechanical 2005
 
Replies continue below

Recommended for you

Brian,
Yes, you can. Right after you check a drawing into the vault, do a “save as” pdf to a directory on your network. This will reset Revisions and Versions onto local drawing. Make this part of your release process and everything will be good.

Bradley
SolidWorks Pro 2008 x64, SP3.0
PDMWorks Workgroup, SolidWorks BOM,
Dell XPS Intel(R) Pentium(R) D CPU
3.00 GHz, 5 GB RAM, Virtual memory 12577 MB,
nVidia Quadro FX 3400
Use SolidWorks BOM
e-mail is Lotus Notes
 
Matt,
Thanks for the vote of encouragement. I have been trying to get management here to do this for years. They always say we do not want to have two data base with the save information. One being the PDM vault and the other directory on the network. Good point.

Bradley
SolidWorks Pro 2008 x64, SP3.0
PDMWorks Workgroup, SolidWorks BOM,
Dell XPS Intel(R) Pentium(R) D CPU
3.00 GHz, 5 GB RAM, Virtual memory 12577 MB,
nVidia Quadro FX 3400
Use SolidWorks BOM
e-mail is Lotus Notes
 
Bradley,

Actually, I was thinking about this. You may not need to create two databases per se. If you are using PDMWorks API triggers, I believe you can make the PDF and copy it to a protected location in one step. It's still two databases, but one drives the other, so the second one always matches the source. I'm sure this can be set up and validated fairly quickly. Just an idea for your situation. The only cost will be in the initial set up, perhaps by a VB programmer with SW experience who can do the the work in a couple of days.

Matt Lorono
CAD Engineer/ECN Analyst
Silicon Valley, CA
Lorono's SolidWorks Resources
Co-moderator of Solidworks Yahoo! Group
and Mechnical.Engineering Yahoo! Group
 
Matt,
Thanks for the idea, a very good one at that.
A star for you.


Bradley
SolidWorks Pro 2008 x64, SP3.0
PDMWorks Workgroup, SolidWorks BOM,
Dell XPS Intel(R) Pentium(R) D CPU
3.00 GHz, 5 GB RAM, Virtual memory 12577 MB,
nVidia Quadro FX 3400
Use SolidWorks BOM
e-mail is Lotus Notes
 
Thanks for the help.

SO would I be able to talk either one of you to create this as they say "pro bono".[bigcheeks]

Brian-CSWA
Dell Optiplex 745
Intel Core 2 6300 @ 1.86 GHz 2 gig Ram
Solidworks 2007 SP 5 & 2008 SP 3.1
AutoCAD Mechanical 2005

 
Brian,
I do not have time right now. Sorry
Although I am sure I need it also, if I could get management to agree first.


Bradley
SolidWorks Pro 2008 x64, SP3.0
PDMWorks Workgroup, SolidWorks BOM,
Dell XPS Intel(R) Pentium(R) D CPU
3.00 GHz, 5 GB RAM, Virtual memory 12577 MB,
nVidia Quadro FX 3400
Use SolidWorks BOM
e-mail is Lotus Notes
 
Status
Not open for further replies.

Part and Inventory Search