MS Project 2007 question

Status
Not open for further replies.

j33pguy

Aerospace
Jun 24, 2009
1
hello,
i'm creating a schedule in project.....and i have the following question: (ps. i'm very new at this)

how do i indicate the predecessor if i have a "task" C that can be started when 'either' task A or task B is completed?


thank you
 
Replies continue below

Recommended for you

Create Linkages between Both task A and B and Task C.

Which every task out of A and B is later will determin the starting date of Task C.

Good luck!
 