Our company standard for a hot tap over 2" states that magnetic particle shall be done. However, it does not state how long after the installation is complete to perform MP. I thought the standard time was after 24 hours. Is 24 hours standard?
Take into consideration that the thickness of the split sleeve is greater than 3/4".