Run1on
Electrical
- Aug 19, 2001
- 17
We have been investigating our power bills and have discovered we are on a 15 min. demand timer arrangement. When our 300 ton chiler starts it develops an inrush current of approx. 800a ( sometimes 1000) As such the demand meter "sees" this point and registers it. Is it possible to install a soft start or VFD to the system to lower this inrush demand and consequentially reduce the demand charge. This piece of equipment is far and away the largest user in the system. The chiller is a Trane RHTB rotary water cooled unit.
Kevin
Kevin