Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations cowski on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Interpreting Design Density Curves

Status
Not open for further replies.

arion

Materials
Nov 22, 2010
42
I found a very interesting article on the historical forming of the NFPA 13 design area curves:


I have crunched through it and found very interesting points that really put the curves into context, but wanted to have a discussion on a couple of points that I could not seem to wrap my head around.

Reference comment: Chester Schirmer's 1972 note states "In 1972, the NFPA 13 light hazard curve extended to an operating area of 5,000 ft2 (460 m2) with a design density of 0.075 GPM/ft2 (3 mm/min). The revision for the 1974 edition resulted in a reduction of the allowable operating area from 5,000 ft2 (460 m2) to 4,000 ft2 (370 m2), at which 0.05 GPM/ft2 (2 mm/min) was indicated as the required design density."

Question 1: What exactly does it imply to have a reduction of the "allowable" operating area (ie: what is "allowable" and why is there a maximum)? If I am at a job site and find a design area of 5,000 sq. ft. on the riser placard, does that mean that the sprinklers need to be recalculated using a 3,000 sq. ft. area, or can I (using Fig. 16.2.1.3.2(b) curve "D" for example) project the .27/5,000 design density/area found at the job site to .27/3,000 on the appropriate curve to validate whether or not the system is adequate enough to protect the commodities? I am interested to hear your thoughts on the implications of this decision of the NFPA to remove all points on figures 16.2.1.3.2(a)-(g) above 3,000 sq. ft. in the NFPA 13 16.2.1.3.2 figures.

Question 2: On that same note of "projecting" square footage, can we treat a single-point density the same way as I described above? That is, (using Fig. 16.2.1.3.2(b) Curve "I" for example), can I project a .42/2,500 design density/area found at the job site to the single-point .42/2,000 requirement at curve "I" to validate whether or not the system is adequate enough to protect the commodities? Also, what are the implications if when on a job site, both density AND area are different than the single point (ie: .49/2,500 found vs. curve "I")? Does the system need to be recalculated in this case?

I am curious about the next plan of action when confronted with these scenarios. Do existing systems designed above 3,000 sq. ft. area = recalculate for 3,000 sq. ft.?

Thanks!
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor