bcbailey
Computer
- Oct 10, 2005
- 3
Hey everyone, can someone help me with slipping tasks in project 2003.
I have a test file that im trying to figure it out with located here
What I want to do, is generate a report where it shows me tasks that are still not finished by todays date, but acording to the baseline, they should be finished. I think that is what slipping tasks does (but feel free to correct me if im wrong).
so in that sample file I have on my website theres only 3 tasks - Build, test, and sell.
Build is 100% done
test is 25% done and according to todays date, it should be 100% done
sell hasnt been started.
I want a report to be generated that says the test stage is slipping. Thats all... can anyone help me?
Thanks alot
--Ben
I have a test file that im trying to figure it out with located here
What I want to do, is generate a report where it shows me tasks that are still not finished by todays date, but acording to the baseline, they should be finished. I think that is what slipping tasks does (but feel free to correct me if im wrong).
so in that sample file I have on my website theres only 3 tasks - Build, test, and sell.
Build is 100% done
test is 25% done and according to todays date, it should be 100% done
sell hasnt been started.
I want a report to be generated that says the test stage is slipping. Thats all... can anyone help me?
Thanks alot
--Ben