lumbee
Mechanical
- Feb 26, 2003
- 15
I have the drawings from a manufacturer for a 40' x 40' metal building. Looking at the worst case scenario(115 mph winds), the uplift would be 7 kips. Won't this make the footing have to be oversized greatly to counteract the uplift force? I am thinking about using a buried spread footing and pedastal combination. This would allow me to use soil to help hold down the footing and minimize the concrete. Does anyone have any suggestions? Can this load be reduced because of it being a wind load?