Hi All!
The client specifys that after two (2) repairs and PWHT ments on a weld , the original weld must be cut out and re-done! I'm in agreement with this, however people are asking where this is stipulated in the code? typically ASME!
Any clues?
Regards
The client specifys that after two (2) repairs and PWHT ments on a weld , the original weld must be cut out and re-done! I'm in agreement with this, however people are asking where this is stipulated in the code? typically ASME!
Any clues?
Regards