humbug
Industrial
- Jul 18, 2002
- 11
Is there a formula to use when performing a "Hot Pull" on piping that has been installed? We have a 30" x 1.125" x 32' +/- Carbon Steel piping that needs to move approx. 1" in the horizontal directional. (This 30' run turns with a 90°ell and continues for apporx. 60' before another break.)
The piping cannot just be moved to compensate this miss due to hangers, supports and struts already installed.
The piping cannot just be moved to compensate this miss due to hangers, supports and struts already installed.