Generating Planned vs. actual progress curve

Status
Not open for further replies.

bmsg

Electrical
Oct 27, 2003
45
Is it possible to generate a planned progress vs. actual progress curve from MS Project? If yes, how?
 
Replies continue below

Recommended for you

Copy the data "work" and "actual work" in the right hand pane of the task usage view into MSExcel and create your graph there. This is the only method I've found to be of any use.
Will
 