Is there a feature in MS Project 2003 that would allow me to create deadlines or constraints that are dependant on the completion of other tasks, not date specific?
Exp...I must send out a notice to proceed 180 days after the pre-constuction contract has been signed. I want to be able to move the contract signing date and have the NTP move as well. Thereby floating the deadline to match.
Thanks