May 14, 2012 I have a question regarding program of work in Fidic 1987. If the Contractor failed to submit a program of work, can the Engineer ask somebody to prepare this program of work for the contractor and ask the contractor to follow it. Click to expand...
I have a question regarding program of work in Fidic 1987. If the Contractor failed to submit a program of work, can the Engineer ask somebody to prepare this program of work for the contractor and ask the contractor to follow it.