Duration Collumn

Status
Not open for further replies.

obede

Computer
Feb 6, 2006
4
Hi, dear

I'm Newbie on MS Project.
I need to create a Collumn similar to Duration Collumn but this collumn needs to maintain fixed values, that is, even when I change the values on Duration Collumn or Actual Duration Collumn this Collumn doesn't change values.
Is it possible?
How can I get it?

Thank you very much.

Obede
Microsoft Office Project Professional 2003 SP1
 
Replies continue below

Recommended for you

What is the content that you want in this new column? I'm a little confused as to what value you are trying to hold constant. "Work" is a function of the number of man-hours involved in a task and will stay constant if the task is "fixed work", no matter what the duration is. Or, are you looking for a "Baseline Duration", which would give you a comparison of the new duration to what was originally planned?

 
Hi,naygoo

I'm reading articles about baseline duration and I think I'll solve the problem. I need to maintain the original value (planned).
Could you tell me where I can get good articles about MS Project.

Thank you very much

Obede
Brazil
 
I'm not sure where else to find articles about MS Project. Personally, I use this forum when I need to, but most of my questions I solve using a book called "Special Edition Using Microsoft Office Project 2003", by Tim Pyron (Que Publishing). Good luck!

 