Indy
Industrial
- Dec 14, 2012
- 172
Hello,
I have a question regarding the design vs operating pressure and temperature in relation to temperature instrumentation (thermowell)on process piping. For example say we have a pipe where the max operating pressure is 7.3 barg and the max operating temperature is around 43 deg C but the design pressure is 16 barg and the design temperature is 60 deg C.
When it comes to the wake frequency calculations I would say that the design conditions should be used as these are the maximum values that the thermowell could see.
Is this normally the case or are the operating max pressure and temperature used?
Thank you
I have a question regarding the design vs operating pressure and temperature in relation to temperature instrumentation (thermowell)on process piping. For example say we have a pipe where the max operating pressure is 7.3 barg and the max operating temperature is around 43 deg C but the design pressure is 16 barg and the design temperature is 60 deg C.
When it comes to the wake frequency calculations I would say that the design conditions should be used as these are the maximum values that the thermowell could see.
Is this normally the case or are the operating max pressure and temperature used?
Thank you