mscatcard
Computer
- Mar 17, 2005
- 2
I need to use a custom timescale for my MS Project schedule - instead of months and weeks I need Period 1 Week 1, Period 1 Week 2, etc. Is there some way to modify the timescale at the top of the gantt chart view to do this? Or is there an easy way to export a gantt chart to Excel so I can do my own timescale?