Hi,
I'd like to try and see if I can have a custom filter work just like the way I've got this example below:
Here's what I've got so far:
Task Name Days Start Resource Names
Analysis 1 day 4 jan jack
Design 1 day 4 jan matt
Building 4 days 24 jan jack
I want the Resources Names as listed above to behave exactly the way I want to when I use "Assign Resources" Dialog box. As you see, Jack cannot do "Design" task, but would be available for "Building" Task. Could you help me now and simplify as to how I can solve this using "Assign Resources" Dialog Box?
I'd like to try and see if I can have a custom filter work just like the way I've got this example below:
Here's what I've got so far:
Task Name Days Start Resource Names
Analysis 1 day 4 jan jack
Design 1 day 4 jan matt
Building 4 days 24 jan jack
I want the Resources Names as listed above to behave exactly the way I want to when I use "Assign Resources" Dialog box. As you see, Jack cannot do "Design" task, but would be available for "Building" Task. Could you help me now and simplify as to how I can solve this using "Assign Resources" Dialog Box?