Civil/Environmental
- Feb 12, 2002
- 3
Greetings,
I am doing a small civil site works project on the side and I want to give the developer a price for the engineering design work. I remember (vaguely)that there exists a "rule of thumb" that states: that the engineering component of the overall project (until the project is complete) is approximately 5-10% of the total cost(generally speaking). If anybody has more insight into this matter I would appreciate their assistance.
Thanks!
I am doing a small civil site works project on the side and I want to give the developer a price for the engineering design work. I remember (vaguely)that there exists a "rule of thumb" that states: that the engineering component of the overall project (until the project is complete) is approximately 5-10% of the total cost(generally speaking). If anybody has more insight into this matter I would appreciate their assistance.