bookowski
Structural
- Aug 29, 2010
- 983
Contract question regarding the transfer of ownership of instruments of service and the implications. The below is from a client contract. I am pushing the client's attorney to remove this language and instead state that the consultant retains ownership but grants the client a royalty free non-exclusive license of the documents in relation to the project. I am not 100% clear on the implications of this though and since I'm arguing with the client's attorney I'm a bit outmatched.
What does it mean to give them ownership (including copyright) of my instruments of service - and why do they even need it? Does this mean they can now say they own my typical beam detail for example and I am infringing every time I use it?
From the contract:
§ 7.7 Following completion of Structural Engineer’s services and Owner’s final payment to Structural Engineer all amounts owed for Basic Services and Additional Services pursuant to the terms of this Agreement, Structural Engineer hereby permanently and irrevocably transfers all ownership of the Structural Engineer’s Instruments of Service including all common law, statutory and other reserved rights, including copyrights, to Owner. Structural Engineer further agrees to execute any documents necessary or reasonably required by Owner to effect or otherwise acknowledge such transfer.
What does it mean to give them ownership (including copyright) of my instruments of service - and why do they even need it? Does this mean they can now say they own my typical beam detail for example and I am infringing every time I use it?
From the contract:
§ 7.7 Following completion of Structural Engineer’s services and Owner’s final payment to Structural Engineer all amounts owed for Basic Services and Additional Services pursuant to the terms of this Agreement, Structural Engineer hereby permanently and irrevocably transfers all ownership of the Structural Engineer’s Instruments of Service including all common law, statutory and other reserved rights, including copyrights, to Owner. Structural Engineer further agrees to execute any documents necessary or reasonably required by Owner to effect or otherwise acknowledge such transfer.