Hello all,
I am in the middle of a very important project - pouring my garage pad. It is an 18' x 24' 4" thick slab, with 8" thickened edges (for one foot in). Since I am installing hydronic heating, the under side of the slab is insulated with 2" rigid foam (R10). I am using 10m rebar for reinforcement as per the Concrete Design Manual.
My problem is this: I want to pour next week. The problem is that at night, it is dropping below freezing a bit (25*F), and warms back up to 50 to 60*F during the day. The ground is not frozen yet. My plan is to lay down plastic sheeting once the concrete has been finished, cover with 12" of straw and cover with a tarp.
My problem is that being in my backyard, I have no way of really hoarding and heating. Given that I am going to use 27.5 MPa concrete with calcium for cold weather curing, can I continue as I plan, or should I pull the plug and wait until spring??
Can anyone think of a good way of taking advantage of using my hydronic heating in some temporary fashion to keep the temperature of the slab up for the first 3 days?
Thanks!
K.A.
Calgary, AB, CA
I am in the middle of a very important project - pouring my garage pad. It is an 18' x 24' 4" thick slab, with 8" thickened edges (for one foot in). Since I am installing hydronic heating, the under side of the slab is insulated with 2" rigid foam (R10). I am using 10m rebar for reinforcement as per the Concrete Design Manual.
My problem is this: I want to pour next week. The problem is that at night, it is dropping below freezing a bit (25*F), and warms back up to 50 to 60*F during the day. The ground is not frozen yet. My plan is to lay down plastic sheeting once the concrete has been finished, cover with 12" of straw and cover with a tarp.
My problem is that being in my backyard, I have no way of really hoarding and heating. Given that I am going to use 27.5 MPa concrete with calcium for cold weather curing, can I continue as I plan, or should I pull the plug and wait until spring??
Can anyone think of a good way of taking advantage of using my hydronic heating in some temporary fashion to keep the temperature of the slab up for the first 3 days?
Thanks!
K.A.
Calgary, AB, CA