Hi;
The CBR test as per the AASHTO method T 193 requires the rate of penetration of piston in to the sample at 1.3 mm/minute uniformly and continuously. When there is no load (without sample) this rate is maintained properly.
When test started with a soil specimen compacted, the rate of penetration is reduced depending on the strength of soil and the specified rate is not maintained. Is this normal or should the machine increases the load maintaining the rate of 1.3 mm / minute automatically? We have tried on many machines but all indicated this problem. Please help.
Thanks
The CBR test as per the AASHTO method T 193 requires the rate of penetration of piston in to the sample at 1.3 mm/minute uniformly and continuously. When there is no load (without sample) this rate is maintained properly.
When test started with a soil specimen compacted, the rate of penetration is reduced depending on the strength of soil and the specified rate is not maintained. Is this normal or should the machine increases the load maintaining the rate of 1.3 mm / minute automatically? We have tried on many machines but all indicated this problem. Please help.
Thanks