Calendar and Non-Working

Status
Not open for further replies.

Arch1234

Civil/Environmental
Dec 6, 2007
1
I client would like to see both the number of working days and overall calendar days. Can I have both? How do I do this?
 
Replies continue below

Recommended for you

Create a Number1 column. Customize with [finish]-[start]. Result is elapsed days.

TTFN

FAQ731-376
 