eric1037
Geotechnical
- Jul 12, 2004
- 376
Ok, I have a lulu of a project. Here's the scenario:
My client is planning on constructing three single-story, slab-on-grade retail structures on a site that has been filled periodically over the past 10 to 12 years. Column loads are in the range of about 80 to 100 kips. One of the structures is a long and skinny strip mall structure and the two others are chain restaurant-type structures. Our client wants to raise grades about 2 to 3 feet.
The soil profile generally consists of 23 to 26.5 feet of fill over 2.5 to 4.5 feet of amorphous peat and/or organic silt and clay. The PT/OL is underlain by clay with shear strengths in the range of about 2 ksf to about 32 feet, then sand with N-values of 25 to 40 to about 50 ft., then sandy silt with N-values in the range of 80 to 90 to 60 ft., then sand with N-values in the range of 80 to 90 to the explored depth of 70 feet.
Groundwater is below the PT/OL at a depth of about 30 feet.
About 18 feet of the fill was placed about 8 years ago. We have spotty compaction tests on the very top that show at least part of the final lift was compacted to 95% of a modified proctor.
N-values in the fill range from about 10 to 58, so it's not in that bad of a condition. However, we did encounter buried debris like pieces of concrete, etc. in the fill. I was also informed that a building previously occupied part of the site and they left an exterior concrete slab and some asphalt pavement in place.
The peat has moisture contents ranging from about 40 to 60 percent with N-values in the range of 16 to 30. Not too shabby. Based on this data, I believe the peat is currently in secondary consolidation.
Based on Schmertmann's method, the stress increase becomes negligible at 2 time the fdn diameter for column footings and 4 times the fdn width for strip footings. Therefore, the stress increase at a depth of 23 feet on the PT/OL should be fairly low, but I know that it doesn't take much stress incress on organic soils to induce settlement.
I am very leary about placing shallow spread footings on the fill, especially with an additional 2 to 3 feet of fill on the site. I haven't gone through the effort of doing a Boussinesq stress analysis yet, but it's my feeling that there will be differential settlement.
I considered auger-cast piles, but I think the downdrag of 23 ft. of sand, gravel, and debris would make the piles very long. Also, the debris and buried slab may make a nightmare out of pile installation.
I have considered double-cased drilled piers with permanent casing, but that just seems like overkill for structures like this.
I have also considered a raft or mat foundation, but one of the structures is a strip mall that is fairly long and narrow and I'm not sure how much it would help. I have asked the architect and structural engineer to consider seperating the individual units to help with differential settlement.
My last consideration is pre-loading the site for an extended period of time, say 6 to 12 months. However, the soil piles would be rather large and it may not fit into my client's schedule. It would present an unknown because we would have to install some instrumentation and monitor the settlement until we are satisified we are well into secondary consolidation. In addition, we would probably have to stage the loading and it could take much longer than anticipated.
There is a ray of hope in that the strip mall building area has not been completely filled and one half of the area is still at the top of peat level. We could potentially excavate the fill out of the area of the strip mall and use it to preload the other building sites. The organics could then be removed and the resulting excavation filled with engieered fill.
Ok, now that you know the situation I would like to know if I am missing anything or if I am being overly cautious. I am of the mindset that building over PT/OL should be done VERY cautiously with no guarantees because of the long term "tertiary" settlement that results from biologic processes and the potential for large differential settlement due to varying thicknesses and physical properties.
Any input?
Thanks in advance!
My client is planning on constructing three single-story, slab-on-grade retail structures on a site that has been filled periodically over the past 10 to 12 years. Column loads are in the range of about 80 to 100 kips. One of the structures is a long and skinny strip mall structure and the two others are chain restaurant-type structures. Our client wants to raise grades about 2 to 3 feet.
The soil profile generally consists of 23 to 26.5 feet of fill over 2.5 to 4.5 feet of amorphous peat and/or organic silt and clay. The PT/OL is underlain by clay with shear strengths in the range of about 2 ksf to about 32 feet, then sand with N-values of 25 to 40 to about 50 ft., then sandy silt with N-values in the range of 80 to 90 to 60 ft., then sand with N-values in the range of 80 to 90 to the explored depth of 70 feet.
Groundwater is below the PT/OL at a depth of about 30 feet.
About 18 feet of the fill was placed about 8 years ago. We have spotty compaction tests on the very top that show at least part of the final lift was compacted to 95% of a modified proctor.
N-values in the fill range from about 10 to 58, so it's not in that bad of a condition. However, we did encounter buried debris like pieces of concrete, etc. in the fill. I was also informed that a building previously occupied part of the site and they left an exterior concrete slab and some asphalt pavement in place.
The peat has moisture contents ranging from about 40 to 60 percent with N-values in the range of 16 to 30. Not too shabby. Based on this data, I believe the peat is currently in secondary consolidation.
Based on Schmertmann's method, the stress increase becomes negligible at 2 time the fdn diameter for column footings and 4 times the fdn width for strip footings. Therefore, the stress increase at a depth of 23 feet on the PT/OL should be fairly low, but I know that it doesn't take much stress incress on organic soils to induce settlement.
I am very leary about placing shallow spread footings on the fill, especially with an additional 2 to 3 feet of fill on the site. I haven't gone through the effort of doing a Boussinesq stress analysis yet, but it's my feeling that there will be differential settlement.
I considered auger-cast piles, but I think the downdrag of 23 ft. of sand, gravel, and debris would make the piles very long. Also, the debris and buried slab may make a nightmare out of pile installation.
I have considered double-cased drilled piers with permanent casing, but that just seems like overkill for structures like this.
I have also considered a raft or mat foundation, but one of the structures is a strip mall that is fairly long and narrow and I'm not sure how much it would help. I have asked the architect and structural engineer to consider seperating the individual units to help with differential settlement.
My last consideration is pre-loading the site for an extended period of time, say 6 to 12 months. However, the soil piles would be rather large and it may not fit into my client's schedule. It would present an unknown because we would have to install some instrumentation and monitor the settlement until we are satisified we are well into secondary consolidation. In addition, we would probably have to stage the loading and it could take much longer than anticipated.
There is a ray of hope in that the strip mall building area has not been completely filled and one half of the area is still at the top of peat level. We could potentially excavate the fill out of the area of the strip mall and use it to preload the other building sites. The organics could then be removed and the resulting excavation filled with engieered fill.
Ok, now that you know the situation I would like to know if I am missing anything or if I am being overly cautious. I am of the mindset that building over PT/OL should be done VERY cautiously with no guarantees because of the long term "tertiary" settlement that results from biologic processes and the potential for large differential settlement due to varying thicknesses and physical properties.
Any input?
Thanks in advance!