sgoris
Civil/Environmental
- Dec 5, 2001
- 1
Has anyone encountered a situation where an unapproved material was used in construction and a reduced payment was the result? The contractor was notified that the material was unapproved after it was placed (concrete in this case). A review of the concrete tickets revealed the admixture though the product code was approved. The material meets code, but contains an admixture not approved through the submittal process. The admixture in this case was a chloride containing admixture placed in reinforced concrete. The contractor was put on notice that the material was not approved and was required to correct the situation. The response of the contractor was to show the material met code. The contractor had the chlorides tested and the chloride content is within ACI standards. The owner now has a material they did not approve of. Is there a basis for reduced payment, i.e. not allowing the cost of the concrete, in this case?