Hello everyone, would love second opinions on a wood truss repair.
I've got a series of wood roof trusses ~5 years old and they show signs of minor splitting at their bottom chord splice locations. See picture below, bit hard to see.
Uniform across almost all the new trusses. To me it appears...
Hi all, does anybody have a design reference for a connection that looks like the one below?
AISC Design Guide 16, flush multiple row end plate moment connections does not cover anything beyond a group of 4 bolts.
I'm wondering if I need to explore and extrapolate the yield lines, etc from...
Hi folks, I've got a wood-framed project where an Architect wants a clean uniform soffit, so we're being asked to up-set some wood beams, leaving their top flange unbraced.
14" deep I-joist framing hangered to beams typically, bottom flush with beams. I'm fairly confident that a small amount of...
I have a 6" total thickness slab over steel deck (4.5" concrete over 1.5" B deck) that has been designed for forklift loading. Following SDI's (Steel Deck Institute) guidelines, the deck is form-only and reinforcing has been provided to support the forklift loading.
The bottom rebar is intended...
Hello fellow engineers, I am in need of some second opinions on a potentially sticky code interpretation issue.
This is in the U.S., governed by IBC 09.
What occupancy category would you assign to the following structure?
Two story steel framed building. The first story consists of two small...
I have an 8 story steel frame building in schematic design. I am running a comparison of an EBF system vs a BRBF system to hand off to the contractor to price out. Both of the systems are being designed under ASCE 7-05 using the fixed beam-column connections for R=8.
We are permitted to have...
New to ETABS and building my first model.
How does ETABS handle the input of snow drift loading? I can't seem to find any options for it. I am dreading that I might have to input tapered loads individually on all my frame members.
On the same note, is there any way to assign, for instance, a...
So I have a situation where a contractor discovered that the previous contractor nailed off some shear walls with the wrong size nails.
My first check I wanted to run was if tightening up some spacing with the same nails would work out, but all the IBC tables are based on common nail sizes...