Has anyone used the resource function to manage tooling requirements in their project. If so, was it organized using the material option or Work?
Thanks!
I have developed a gigantic project file that has required some rearranging. However, now that I have assigned the WBS codes to it - it chooses to use the initial ID Number as the contributer to how it assigns the WBS Code. Is there a way to Re-Order the ID Numbers to fit the order the project...