  1. ppmsb

    Unit Cash Cost for Cogeneration Plant

    Hi, I was requested to calculate the UCC for our newly installed Cogen Plant (4 GTGs + 1 STG) and to compare with the charges by the utility power company. Below is the sample of calculation. Post Cogen : RM 68.2/MW-hr or USD 20.1/MW-hr Utility Company : RM 220.5/MW-hr or USD 64.9/MW-hr...
  2. ppmsb

    Unit Cash Cost (UCC) for Cogeneration Plant

    Hi, I was requested to calculate the UCC for our newly installed Cogen Plant (4 GTGs + 1 STG) and to compare with the charges by the utility power company. Below is the sample of calculation. Post Cogen : RM 68.2/MW-hr or USD 20.1/MW-hr Utility Company : RM 220.5/MW-hr or USD 64.9/MW-hr...
  3. ppmsb

    IGCC for the Refinery

    Hi, We are planning to construct a 250,000 BPSD refinery. For power/steam supply we are also planning to install IGCC as an integrated facilities with the refinery. Anyone got previous experiences on IGCC within a refinery. We anticipate a 200MW IGCC. Thanks ppm
  4. ppmsb

    IGCC Technology

    Anyone to share knowledge & experience on Integrated Gasification Combined Cycle (IGCC) technology? ppm
  5. ppmsb

    Fuel Gas Composition

    Hi, The GTG is designed based on certain composition of gas. Currently we don't have monitoring device to check the gas composition entering GTG. What is the impact to GTG if there is significant changes on the gas composition? ppm
  6. ppmsb

    Fuel Gas Temperature to GTG

    Hi, Currently our fuel gas skid got heater to ensure/control fuel gas temp entering GTG combustor at 42 C. If the heater fail/trip & let say the FG temp reduces below 30 C, what is the impact to GTG? Was told the GTG will trip? What the normal criteria of FG temp? Thanks ppm
  7. ppmsb

    Provision of Bypass Stack

    Hi, What are the criteria to install bypass stack between GT and HRSG? ppm
  8. ppmsb

    Provision of OEM GTG Engrs/Specialist - Installation/Commissioning

    Hi, We are planning to engage OEM engr/specialist for the supervision for installation, commissioning and performance testing of our gas turbine package. The contract will be on reimbursable basis i.e. manhour rate. Any advise on how to effectively manage this type of contract? Any lessons...
  9. ppmsb

    Requirement for Remote Control Unit (RCU) for small motor

    Hi, Our company standard states the following requirements: "Electric drives shall be provided with an RCU mounted local to the motor. By means of this RCU, motors can be started/stopped and, in the "O" (neutral) position, automatically control" Is this common practice even for small LV motor...
  10. ppmsb

    Instrument Protective Function (IPF) Review

    Hi, We are planning to do IPF review on our cogeneration project. But I'm just skeptical on the usefulness of the review? Anyone got something to share ppm
  11. ppmsb

    Gas Turbine Efficiency

    Hi, Anyone know what is the highest industrial & aeroderivative type GT efficieny in the market now? ppm
  12. ppmsb

    Foundation Fieldbus

    Hi, Anyone got experience with foundation fieldbus system. We had experience some communication problem with the Rotork actuator. ppm
  13. ppmsb

    Commissioning of Condensing Steam Turbine Generator

    Hi, We are going to commission a 25MW condensing STG soon. Any experience to share ppm
  14. ppmsb

    Online Tie-In for DCS/SGS

    Hi, I'm doing a cogeneration expansion project. For the existing cogen project we use Honeywell Experion for the DCS/SGS to monitor and control 4 trains of GTG/HRSG and 1 train of STG. For the cogen expansion project, we plan to install one additonal train of GTG/HRSG. Hence we need to...
  15. ppmsb

    Machine Monitoring System 1 (MMS) Rev 5 & Rev 6

    Hi, For our recent cogen project (now under commissioning phase), we have installed MMS System 1 Rev 5 for monitoring of the vibration for gas/steam turbine. It was supplied by BN. Also we have the intention to expand the cogen by installing one more gas turbine. Was informed by the eqpt...
  16. ppmsb

    Control/Signal Cable Length Requirement for Gas Turbine

    Hi, Was informed by the vendor that there is a max of 300 m cable length requirement from transmitter sensor to terminal point at rack room. Any similar experience? Thanks ppm