  1. smwa

    Use of Steel SMF in Wood Frame Building

    I'm curious about how to brace the hinge points in a Reduced Beam Flange Special Moment Frame with a wood diaphragm. I've seen a lot of steel angle braces back to the wood diaphragm, but it doesn't seem like the wood diaphragm will be able to resist the code required brace load (6% of beam...
  2. smwa

    ACI 318-08 Appendix D

    I'm curious if anyone has read the new ACI318-08 Appendix D, Section D3.3.6? Am I understanding correctly that if the anchor material is brittle, then the anchor design strength is limited to 0.4 x concrete failure strength per D3.3.3? Why is the brittle anchor design strength a function of...
  3. smwa

    Wood Dry Rot Repair Specifications

    Hi All, I'm involved with a multi-unit housing retrofit project which includes dry rot repair for many of the architectural elements. I'm wondering if there are general specifications for dry rot repair that I can use as a starting point. I looked into Masterspec index and didn't see anything...
  4. smwa

    Weldable Rebar Coupler

    Does anyone have recommendations for weldable rebar coupler? I have used Lenton weldable mechanical coupler in the past. However, I just found out that they don't have a current ICC-ER report for IBC. Are there other options for weldable couplers? I'm using the coupler to attach rebars to...
  5. smwa

    Foundation Design for Fixed Base Steel Moment Frame

    I'm currently designing a school building with Special Steel Moment Frames. The columns of MF run through the depth of a 30" deep mat slab and sits on a bearing pad below the mat slab. I used fixed condition at the base in the MF analysis to limit the drift. My question is, do I need to to...
  6. smwa

    Topping Slab for Mat Foundation

    Hi All, I'm designing a mat foundation with a 5" topping slab. The topping slab is added so the architect can depress the finish elevation for walk-off mats and restroom tiles, and also coloring the topping slab w/o coloring the entire mat. My question is: Should the topping slab be poured...