I recently received a request to provide grounding specifications and detail drawings for several new cantilever gates and several new full height rotating turnstiles at a power plant. I have found enough information on several options for grounding the cantilever gates, but I have found nothing...
Howdy all,
Does anyone know how an ITI model 780 600:5 CT will perform at very low load - such as 3% of rating? A customer has this CT installed in a metering and overcurrent relaying application and they will not take a bus shutdown to change it to a lower ratio CT. They plan on installing a...