Hi all,
I am going to change out a section of corroded piping, since hotwork is not allowed thus I will go for "like for like" replacement with same new piping material but fittings component will be using "compression swaging" type fittings. Do I need to do piping stress analysis for this case?
Dear all,
I have a few heat exchanger flanges found cracked possibly due to over-torqued and victim of hydrogen sulfide stress cracking, the operating temperature is between 45 to 129 deg C.
I can't shutdown the line for replacement, is there any ways to temporary repair these flanges and...
Hi all,
I need to repair the angle steel and I-Beam which are heavily corroded plus metal loss, it is for overhead pipe rack, this is an old LNG plant where these steel structures had never been changed since the last 25 years. I'm currently looking at repairing these steel structure by using...
Hi all,
I need to repair the angle steel and I-Beam which are heavily corroded plus metal loss, it is for overhead pipe rack, this is an old LNG plant where these steel structures had never been changed since the last 25 years. I'm currently looking at repairing these steel structure by using...