In precast beam-column moment connection where precast beam is resting on corbel of precast column and top rebars of beam are made continuous through precast columns in top cast-in-place part of precast composite beam, is it necessary to continue some of the bottom bars of precast beam through...
In my ACI318m-11 (metric version), clause 10.6.7, the requirement of skin reinforcement arises if beam depth is more than 400mm. Can any body check? What I remember, it was 900mm (36") in previous codes. If this is a typo, is it covered in errata?
IR
I am working on a housing scheme which consists of 2 story small buildings which are all repetitive. The scheme is to use precast planks(may be hollowcore or solid)resting on load bearing wall panels (External are sandwich panels). To speed up the work, client is suggesting to remove/minimize...
I am designing an underground circular water tank which will be built in rocky strata. The tank is almost 30 meters deep and 25meter in diameter. Due to high strength rock (Limestone). Water table is not an issue, its just 2 to 5 meter from bottom of tank but seasonal variation may exist. I have...
I am designing an underground circular tank for water retention. Its a big storm water tank. It has 25 meter diameter and 30 meter deep. The outer strata is rock (qu=20000 to 25000 KN/Sqm), its lime stone. Its dry density is almost as of hardened concrete, i.e 2.46 MN/m3. Water table is also not...