I am looking for a transmission protection and Control training in Canada or US. Someone refered me to this course offred by Univirsitry of Wisconsin. Has anyone attended this course who can provide a feedback?
http://epdfiles.engr.wisc.edu/pdf_web_files/epd/P018.pdf
Thank you
I always thought that the CT accuracy class defines the metering or protection class and not the Burden.
A 600/5 CT with B=0.1 is used for protection in this case.
One of our customers is upgrading their electrical system by replacing a 2.5MVA transformer to 5 MVA transformer ( 27.6kV primary). I am wondering if there is a CEC requirement to install a breaker on the primary side of the new transformer instead of a disconnect switch?
Thanks for all feedbacks
We are designing a 230kV substation and wondering if there are any code/standard requirements in Canada to provide certain horizontal distance from de-energized parts a 230kV substation equipment ( such as A-Frame) to the substation fence?
GPR level is acceptable. Step and touch are not within the limits, so my question is whether modeling the existing substation ( which is taking a long time) and connecting it to the existing grid would change the S&T potentil values of the new subtation or as pwrtran indicated we just have to...
We are building a small substation ( including a transformer and a padmount switchgear) in adjacent to a wind farm substation and connecting the new substation ground grid to the existing grid. The existing grid has a measured grid resistance of .5 ohms. we are using Cymgrd to model our...
We are working on a project and need to define typical ( conservative ) impedance values for Delata-Wye and Wye-G, Wye-G, Delta transformers. Transformers are 18/25/30 Mva 230kV/34.5 kV. Where can I find these typical values?
I apprecite your responces.
CEC suggests specific arrangements for underground cable installations in section B4. I am working on a design which specifies 6C/phase cables in 6 conduits.
Our preferred arrangement to accommodate installation flexibility is to have all phase-A, B and C cables installed in one duct bank...