  1. Murali27

    Shell Structure - FEA software

    Dear All I am looking for suitable FEA software to deal with Shell Structure. (roof shell structure (concrete/steel) and supporting numerous vertical loads) Resulted in two modules (ABAQUS or TNO DIANA). Any feed back will be useful to choose relevant sotware to deal with this structure...
  2. Murali27

    Shearwall reinforcement detail - Non seismic region

    Thanks for your reply, i agree that vertical bars could be outside, if it is a retaining walls/where out-of plane moment is significant, we can also achive high lever arm.
  3. Murali27

    Shearwall reinforcement detail - Non seismic region

    Dear All Typically the vertical bars will be inside (far face) and horizontal bars outiside (near feace) in load bearing walls, horizontal bars provide concrete confinement. Any one has come across the detail vice versa, i.e., vertical bars outside and horizontal bars inside. Regards Murali
  4. Murali27

    Seismic Site Classification

    Seismic site classification reflects (defines) how the seismic waves (acceleration) amended (amplified or reduced) when it hits at base of structure. Soil classification basically amends the spectral accelerations. Foundation type should not change seismic site classification. Having said that...
  5. Murali27

    A rule of thumb for pier labelling of shearwall.

    Yes, it shouldn't affect any analysis results. Pier labelling is mainly for design purposes.
  6. Murali27

    Calculation of structural period for using in UBC 97 seismic force

    In static method approach in ETABS as per UBC 1997, it also restricts the actual time period based on modal analysis to 1.4 x Method A time period or 1.3 x Method A time period.
  7. Murali27

    Shear Wall Results

    Hi Structech08 1a) Pier design: The shear reinforcement reported in the design is total reinforcement (for wall, it is total horizontal steel). 1b) Spandrel design: The shear reinforcement reported in the design is total reinforcement (for wall beam/beam, it is total vertical steel,i.e., shear...
  8. Murali27

    Design standards at Cairo -

    Thanks for your input The scheme is 10 story residential block in cairo. The few local codes are not in english version. I am looking for especially the seismic code. Cheers
  9. Murali27

    Design standards at Cairo -

    Dear All I am working on structural scheme for cairo,egypt. a) Seismic loads , reference document b) max / min concrete grade used c) grade for steel (rebar) d) structural steel grade (S275 / S355)? e) seasonal variation of temperature Any help will be appreciated.
  10. Murali27

    Maximum Reinforcing - ShearWall Boundary

    We could use mechanical splices to improve buildability. I have also come across with MMFX steel with 80 ksi strength. If possible, the size of boundary element could be adjusted to bring down the precentage of steel.
  11. Murali27

    Modeling for opening

    Hi AlphaXY It appears that there is an issue with structure. Sure you could review point displacements or modal displacements to locate the issue exactly. It may be due to meshing especially in transfer column condition. Please also ensure the right definition of slab type (membrane or shell)...
  12. Murali27

    Colums release and columns to beam joint in etabs

    Hi Seny It may help by idealizing partial fixity to column B base (full moment capacity may not be achieved). I used to pin the base of floating column and design the beam to absorb all the moment/shear. Nominal moments will be transferred to columns above or below. (may not be ideal if this is...
  13. Murali27

    Precast columns - tall buildings

    Dear All In one of our building, contractor proposed to use Precast columns to speed up the programme. These columns are gravity columns and the building is in non-seismic zone. Your input will be appreciated.
  14. Murali27

    Steel Canopy

    Apologies for that, this is a over the full height of the building. Thanks for your input.
  15. Murali27

    Steel Canopy

    Yes, this is a new building, 30 stories. Columns are heavily loaded subjected to shorten around 20 mm after we attach the canopy, due to secondary effects. Can we come out of this issue with slotted holes in embedded plate?