What are the factors to consider to determine the cause of failure of boiler steam drum gasket during testing of safety valve at 1450 psi, our normal working pressure is 1350 psi.
Thanks all
Your contribution has been helpful! found it though - "Safe Hot Tapping Practices in the Petroleum & Petrochemical Industries" API Recommended Practice 2201, 5th edition Section 9
I am aware of both approaches to the task;
I've heard of Keeping the tank filled to maximum/fill trip level and then weld only below this level.
I know of Draining degassify and clean the tank then do the welding.
I have welded on active bunker c tanks and pipelines before but I am more...
Hi all
Is there a code, procedure for welding on an in-service AST diesel oil tank. We are installing fire protection around these tanks in the form of fixed water spray cooling rings & foam top surface discharge. The need for welding is for the brackets that will support the cooling rings.
I...
We are designing a submarine pipeline to transfer heavy fuel oil from a off-shore mooring. Does anyone here has a reference chart on the viscosity of HFO no. 6 (bunker c)at various temperatures. We are aware of the temperature at offload and the related viscosity, however after pumping, and some...
We are designing a submarine pipeline to transfer heavy fuel oil from a off-shore mooring. Does anyone here has a reference chart on the viscosity of HFO no. 6 (bunker c)at various temperatures. We are aware of the temperature at offload and the related viscosity, however after pumping, and some...
We are designing a submarine pipeline to transfer heavy fuel oil from a off-shore mooring. Does anyone here has a reference chart on the viscosity of HFO no. 6 (bunker c)at various temperatures. We are aware of the temperature at offload and the related viscosity, however after pumping, and some...
Hi All
Is there anyone here whom have completed the PMI course - Certificate in Applied Project Management offered through Boston University?
Secondly, if you are charged with a project to develop a methodology to launch and open field offices for a worldwide distributor, what would be the...
What would be the best method to de-oil a 10 inch diameter, 2250 meters long length of submarine pipeline filled with #6 heavy fuel oil. The pipeline is being decommissioned & removed from service.
Taking cost effectiveness & environmentally friendly into consideration
Start by carrying out a condition assessment. Keep it limited to just theoretical analysis, visual defects, do some NDT, no demolition such as cores. Look at what changed in the bldg history and what changed in terms of loading, occupany change of use of spaces. Vibration can be induced by some...
The unit turbine as well as generator has continuous vibration indicators installed. Despite the turbine never exceeding allowable, if there was vibration on the turbine due to a gearbox between the turbine and the generator shafts these vibrations would not be transfered either way, thus...
Analysing the failure which theoretically could derive from: Insufficient development of anchor bolts, as well as insufficient steel detailing to transmitt load or capacity of steel reinforcement design, these are all design shortcomings. The question now is; how liable is the principal...
I just finished reviewing the article "from experience Alternatives to ACI 318-02 July 2004" and it actually speaks to the exact same thing. The problem is how to go about doing this with considerable demolition & downtime. Considering Steel Dowells with a nut at the end in a high strenght &...