Hi,
I'm trying to create a filter or a formula based on
resources available for the entire duration of a task.
if the resource is 100% in units available, then his
name should be visible in the Assign Resources Dialog
Box. Basically, trying to see if we can dynamically
create a custom filter...
Hi,
I'd like to try and see if I can have a custom filter work just like the way I've got this example below:
Here's what I've got so far:
Task Name Days Start Resource Names
Analysis 1 day 4 jan jack
Design 1 day 4 jan...
Dear Support,
How are you? I just saw your website and thought if
you could help me with a MS-Project problem:
I want to design an "Assign Resources" dialog box effectively that could pick resources available for a task. My guess is you might need to use a custom filter and a formula to...
Hi,
I just have a very small question on MS-Project.
I've tried this several times and it hasn't worked
yet.
Basically, I have a Task A and Task B.
Task A starts on Monday for 1 day
Task B starts on Monday for 2 days.
Then I have two Resource Names.
Resource A is assigned to Task A.
Then...