    24 hr- (2 shift) Resource Sheet

    On a 2 shift project (2 x 12 hr shifts per day) what are the numbers of resources do I need to input as the "max units" I have the following numbers per shift: 7 fitters 17 pressure welders 6 welders 10 riggers 10 labourers Are these the correct "max units" I use or do I need to double up for...
  2. johnbeavis

    Start & Finish

    Hi I am doing a boiler shutdaown, working 2 x 12 shifts for 14 days, is it possible to change the start & finish columns from Friday 19/06/09 to 8:00 pm 19/06 format? Thanks.