On a 2 shift project (2 x 12 hr shifts per day) what are the numbers of resources do I need to input as the "max units"
I have the following numbers per shift:
7 fitters
17 pressure welders
6 welders
10 riggers
10 labourers
Are these the correct "max units" I use or do I need to double up for...
Hi
I am doing a boiler shutdaown, working 2 x 12 shifts for 14 days, is it possible to change the start & finish columns from Friday 19/06/09 to 8:00 pm 19/06 format?
Thanks.